Three dishes. One kitchen. Two very different timelines.
A restaurant gets an order: salad, steak, dessert. Chef A makes the salad, then the steak, then the dessert. 45 minutes. The customer leaves a one-star review.
The same restaurant, different night. Three chefs. One makes the salad. One grills the steak. One preps the dessert. 15 minutes. Five-star review.
But the next order is a steak with a pan sauce made from the steak drippings. Now the sauce DEPENDS on the steak finishing first. Three chefs can't help -- the sauce chef has to wait.
Independent tasks fan out. Dependent tasks chain. This decision changes everything.